AWARDED PROJECT


Project Title:   REPLACE SUMP TANKS, SUMP PUMPS AND CONTROLS, B4035
Project Location:   MCAS CHERRY POINT, NC
Contract Number/ Project No.:   N40085-07-D-1908/0102  ST194-07    CCD = 300 DAYS = 3/19/2010
Program:   GMACC 

DRAWINGS: PLANROOM/296 B4035 SUMP PUMPS AND CONTROLS CP SB/Drawings - ST194-07.pdf
SPECIFICATIONS: PLANROOM/296 B4035 SUMP PUMPS AND CONTROLS CP SB/RFP - Replace Sump Pumps, Tanks and Controls B-4035.pdf
ANSWERED RFI: QUESTION: The pump spec describes a pump that is different from the pumps that are in place now - in speaking with pump
suppliers I have been told that the pumps in the specs are not typical for this application and most likely will not
function properly. Please advise what type of pumps are desired for the new sumps, like existing or per Specs?

ANSWER: NEW PUMP SYSTEMS ARE TO BE SIMILAR TO EXISTING PUMP DESIGN AND INSTALLATION


QUESTION:  Is the environment in the basement classified as requiring the controls and pumps to be explosion proof,
intrinsically safe, or both?

ANSWER: OUR UNDERSTANDING THAT NO SPECIAL PROVISIONS ARE REQUIRED FOR WORK IN EQUIPMENT IN THE BASEMENT


QUESTION:  What type of training and PPE will be required for personnel working in the basement area, including cutting pipes
and removing tanks containing hazardous materials? 

ANSWER: OUR UNDERSTANDING IS THAT SPECIAL TRAINING IS NOT REQUIRED FOR THE BASEMENT.  CONTRACTOR IS TO COMPLETE WORK IN
ACCORDANCE WITH FEDERAL (TO INCLUDE MCAS CHERRY PT), STATE, AND LOCAL REGULATIONS AND REQUIREMENTS

QUESTION:  Will the building occupants assure that the pipes and tanks to be removed are empty? Does the contractor have to make
any provisions for disposing of hazardous materials other than contaminated items being removed (Such as any liquids in
tanks etc.)?

ANSWER: OUR UNDERSTANDING IS THAT MCAS CHERRY PT WILL REMOVE/PUMP OUT AS MUCH OF THE STORED MATERIALS AS POSSIBLE AND THE
CONTRACTOR WILL BE RESPONSIBLE FOR REMOVING THE REMAINING MATERIALS. THE REMOVED MATERIALS ARE THEN TURNED OVER TO MCAS
CHERRY PT FOR PROPER DISPOSAL. NOTE, THERE ARE MATERIALS, SUCH AS ELECTRICAL CONDUIT/WIRING, THAT DO NOT REQUIRE SPECIAL
HANDLING/DISPOSAL. THESE MATERIALS ARE THE RESPONSIBILITY OF THE CONTRACTOR TO PROPERLY DISPOSE OF OFF-SITE.
 
QUESTION:  In Spec section 40 95 00 paragraph 2.3.1 the tank level instrumentation calls for 3 level transmitter relays 1 for
low level the 2nd for high level and the 3rd for a fault situation such as loss of power or sensor failure etc. The
drawing details show a low level, a high level and a high- high level indicator. The question is exactly how many level
transmitter relays will be required per tank. Will we be
required to provide the low, high and       high-high indicators plus a
fault indicator?

ANSWER: CONTRACTOR SHALL FOLLOW THE INSTRUMENTATION REQUIREMENTS AS INDICATED ON THE DRAWINGS - LOW, HIGH, HIGH-HIGH, AND FAULT
INDICATION

 

  

These files are in Adobe Acrobat PDF format.